Innovative Construction

 

MALAYAWATA STEEL BEHAD

Prai,Penang

MALAYAWATA STEEL

Construction and completion of the substructure and superstructure works to the proposed No 2 Steel Making plant and ancillary structures for Malayawata Steel Berhad as the main general contractor inclusive of

          Civil works, inclusive road and drainage 

          Reinforced Concrete Structures 25,000 cum with the largest single pour at 500 cubic meters

          Structural Steel 6,500 tons including 2,500 tons of Built Up sections

          Architectural works 

          Civil construction included the construction of a Ferro Alloy pit and a Sludge Pit of up to 12metere in excavation in Marine Clay with a water table 300mm below ground level.

Contract is valued at RM 36 million

Duration of Project: 14 months


MALAYSIAN SHEET GLASS BERHAD

Pasir Gudang, Johor

 MALAYSIAN SHEET GLASS

Proposed JB2F Plant on PLO 435, Zone II, Mukim Plentong, District of Johor Bahru, Johor for Messrs. Malaysian Sheet Glass Berhad.

This factory was constructed in Pasir Gudang under the supervision of the clients representative and Consulting Engineers Tahir Wong Sdn Bhd of Kuala Lumpur.

We were the main contractors for this Pilkington Float glass factory that included Site Preparatory work, Piling and Substructure works, Reinforced Concrete and Steelwork and all Architectural Finishes. Our scope of work included the fabrication and installation of high value Furnace Support Structural Steelwork.

Contract is valued at RM 25 million

Duration of Project: 11 months
 


NIPPON ELECTRIC GLASS (MALAYSIA) SDN BHD

NIPPON ELECTRIC GLASS

Structural steel fabrication and erection for Nippon Electric Glass Phase 4 & 5 - Kajima Corporation being the main building contractors for this project.

Structural Steelwork for NEG 3 2,500 tons Structural Steelwork for NEG 4 2,500 tons Structural Steelwork for NEG 5 700 tons. Fast track project for Nippon Electric Glass in Shah Alam. Our scope included the procurement, fabrication drawing preperation, fabrication and erection of the plant structure in this project.

Contract is valued at RM 7 million

Duration of Project: 4 months


Schutz-DSL Malaysia

Nilai, Negeri Sembilan

 

 

DSC00840

 

IMG_4495

IMG_0338

 

 

Welcome!

Photos

 

MORE PHOTOS (ACM)

 

MORE PHOTOS (MSG)

 

MORE PHOTOS (MYS)

 

MORE PHOTOS (IKM)

 

MORE PHOTOS (OTEC)

 

MORE PHOTOS (Carlsberg)

 

MORE PHOTOS (Kayaba) 

 

MORE PHOTOS (Fbtx) 

 

 